Guonengfa Science and Technology Regulation [2021] No. 47
The energy bureaus of all provinces (autonomous regions and municipalities directly under the Central Government), the Development and Reform Commissions of relevant provinces (autonomous regions and municipalities) and Xinjiang Production and Construction Corps, all dispatched agencies, State Grid Corporation of China, China Southern Power Grid Co., Ltd., and Inner Mongolia Electric Power (Group) Co., Ltd.:
In order to standardize the management of new energy storage projects, promote the active, stable, healthy and orderly development of new energy storage, promote the construction of new power systems with new energy as the main body, and support the realization of carbon peaking and carbon neutrality goals, we organized the compilation of "New Energy Storage". Project Management Specifications (Interim)" is hereby issued to you, please implement it carefully.
Please inform our bureau (Department of Science and Technology) of the implementation situation and suggestions in a timely manner.
Energy Board
September 24, 2021
Management Specifications for New Energy Storage Projects (Interim)
Chapter 1 General Provisions
Article 1 In order to regulate the management of new energy storage projects, promote the orderly, safe and healthy development of new energy storage, and support the construction of a new power system with new energy as the main body, in accordance with the Electricity Law of the People's Republic of China and the Administrative License of the People's Republic of China This specification is formulated in accordance with laws and regulations such as the Law, the Regulations on Electric Power Supervision, the Regulations on the Administration of the Approval and Filing of Enterprise Investment Projects, and the Guiding Opinions on Accelerating the Development of New Energy Storage.
Article 2 This specification is applicable to energy storage projects that export electricity as the main form and provide external services except pumped storage energy.
Article 3 The management of new-type energy storage projects adheres to the principles of safety first, standardized management, active and prudent, including planning and layout, filing requirements, project construction, grid connection, dispatching operation, monitoring and supervision and other links.
Article 4 The competent energy department of the State Council is responsible for the planning, guidance, supervision and management of new energy storage projects nationwide; local energy competent departments, under the guidance of the energy competent department of the State Council, establish and improve the management system of new energy storage projects in their regions, and are responsible for new energy storage projects in their regions Development and supervision and management; the agency dispatched by the National Energy Administration is responsible for supervising the implementation of new energy storage policies, grid-connected scheduling, market transactions and operation management in the region.
Chapter 2 Planning and Guidance
Article 5 The competent energy department of the State Council is responsible for formulating the national new energy storage development plan. According to the national energy development plan, power development plan, renewable energy development plan, energy technology innovation plan and other relevant documents, on the basis of demonstrating the development foundation, development needs and the economics of new energy storage technologies, actively and steadily determine the national new energy storage technology Development goals, overall layout, etc.
Article 6 The provincial energy authorities shall, in accordance with the national new energy storage development plan, in accordance with overall planning, adapting measures to local conditions, leading by innovation, leading by demonstration, leading the market, and developing in an orderly manner, based on the principles of safety and standardized management, study the key tasks of the region and guide The development of new energy storage in the region.
Article 7 The provincial energy authorities shall organize and carry out research on the development scale and layout of new energy storage related to the safe and efficient operation of the power system in their region, and guide the construction of new energy storage projects scientifically and rationally.
Chapter 3 Record-filing Construction
Article 8 The local energy authorities shall implement record-filing management for new energy storage projects in their regions in accordance with relevant investment laws, regulations and supporting systems, and send a copy of the record-filing of the projects to the offices of the National Energy Administration.
Article 9 The filing contents of a new energy storage project shall include: basic information of the project unit, project name, construction site, construction scale, construction content (including technical route, application scenarios, main functions, technical standards, environmental protection and safety, etc.), total project investment Amount, the project complies with the industrial policy statement, etc.
Article 10 After the completion of the filing of a new energy storage project, various construction conditions shall be promptly implemented, and construction shall be started in time after completing other relevant construction procedures required by laws and regulations.
Article 11 For a new-type energy storage project that has been put on record, if the legal person of the project changes, the project construction site, scale, or content changes significantly, or the project construction is abandoned, the project unit shall promptly notify the project filing authority and revise the relevant information.
Article 12 The construction of new energy storage projects shall comply with relevant management regulations and standards and requirements, and the units undertaking project design, consultation, construction and supervision shall have the corresponding qualifications stipulated by the state.
Article 13 The main equipment of new-type energy storage projects shall meet the requirements of relevant standards and specifications, and shall pass the testing and certification of corresponding qualified institutions, and network-related equipment shall meet the relevant technical requirements for safe operation of the power grid.
Article 14 Relevant units of new energy storage projects shall strictly perform project safety, fire protection, environmental protection and other management procedures in accordance with the requirements of relevant laws, regulations and technical specifications, and implement safety responsibilities.
Article 15 To build a new power battery cascade utilization energy storage project, the concept of the full life cycle must be followed, and a battery consistency management and traceability system must be established. The built and new power battery cascade utilization energy storage projects must establish an online monitoring platform to monitor battery performance parameters in real time, conduct regular maintenance and safety assessments, and make emergency plans.
Chapter 4 Grid-connected Operation
Article 16 Power grid enterprises shall, according to the new energy storage development plan, coordinate the planning and construction of supporting power grids. The supporting power grid project should be coordinated with the construction of new energy storage projects. Energy authorities at all levels are responsible for coordination.
Article 17 Grid enterprises shall provide grid access services for new energy storage projects in a fair and non-discriminatory manner. Power grid companies should establish and improve the grid connection procedures for new energy storage projects in accordance with the principles of active service, simplicity and efficiency, and provide grid connection services for new energy storage projects that have been filed.
Article 18 Before a new energy storage project is connected to the grid and commissioned, relevant procedures shall be completed in accordance with the relevant national regulations on quality, environment and fire protection. Power grid companies should clarify the grid-connected commissioning and acceptance procedures in accordance with relevant standards and specifications, and actively cooperate with the grid-connected commissioning and acceptance of new energy storage projects.
Article 19 Power grid enterprises shall, in accordance with the requirements of laws, regulations and technical specifications, take systematic measures to optimize the dispatching operation mechanism, give priority to the deployment in a scientific manner, ensure the utilization rate of new energy storage systems, and give full play to the role of new energy storage systems.
Article 20 New-type energy storage project units shall, in accordance with relevant standards and specifications, be equipped with necessary communication information systems, upload operating information to the power grid dispatching department according to procedures, and accept dispatching instructions.
Article 21 The project unit shall do a good job in monitoring the operation status of new energy storage projects, monitor the operation conditions of the energy storage system in real time, and organize demonstration evaluation and evaluation in a timely manner when the project reaches the design life or the safe operation status does not meet the relevant technical requirements. Correction work. If the relevant requirements are still not met after rectification, the project unit shall take decommissioning measures in a timely manner and report to the original filing authority and other relevant units in a timely manner.
Chapter V Monitoring and Supervision
Article 22 The energy department of the State Council is responsible for building a national new energy storage management platform, realizing the information management of new energy storage projects across the country, and taking the actual construction and operation of new energy storage projects as the basis for formulating industrial policies and improving industry norms and standard systems. important basis.
Article 23 Local energy authorities, in conjunction with relevant departments, strengthen the construction of the monitoring and management system for new energy storage projects, and research and regularly announce the development scale and construction of new energy storage projects based on the filing, construction, operation, and market transactions of new energy storage projects in the region. Layout, dispatch and operation, etc., guide the scientific and rational investment and construction of new energy storage projects.
Chapter VI Supplementary Provisions
Article 24 The National Energy Administration is responsible for the interpretation of this specification.
Article 25 This specification shall be implemented from the date of promulgation.